Agricultural Production Complex
Dnipropetrovsk Oblast
Key features
Facility:
Cogeneration Gas Plant (КГУ)
Status:
Put into operation
Products:
10 kV/5 MV Substation Based on CSM, KZO chambers (КЗО)
Power:
2,535 kW/10 kV
Operating mode:
Parallel
Description
Objective:
Our company's role:
- Design and integration of КГУ into the existing power grid (Electrical engineering solutions, РП, and power grids)
- Construction work (Installation and connection of КГУ, РП, and power grid installation)
- Configuration of 10 kV relay protection
- Commissioning
Features of the relay configuration:
- 10 kV longitudinal differential protection: synchronization of protections between the КГУ and the РП.
- Adjustment of protection zones to ensure selectivity
Gallery of the project
Switchgear Equipment Plant
We don't limit our clients to standard options: our engineers create customized solutions that take into account the technical and operational specifics of each facility.
You may be interested
return to all projects
Cogeneration
Agricultural Production Complex
Facility: Cogeneration Gas Plant
Dnipropetrovsk Oblast
Cogeneration
Agricultural Production Complex
Facility: Cogeneration Gas Plant
Kyiv Oblast